The Birck Nanotechnology Center will be undergoing a closure involving major electrical repairs and completion of our semi-annual preventive maintenance from October 14 through October 18, 2019. 

There will be a major electrical power outage involving all research equipment in the center. During our electrical bus duct failure back in February is was discovered that main power to all research equipment has the same issue that caused the failure in February.

ELECTRICAL work is scheduled from  8 a.m. to 3 p.m. Monday, October 14, 2019.  EVERY GENERAL LAB, MAIN CLEANROOM & BIO CLEANROOM AREAS WILL LOOSE POWER TO RESEARCH EQUIPMENT DURING THIS TIME.  ALSO ALL BUILDING WIDE MAJOR UTILITIES WILL BE LOST INCLUDING Compressed Air, Process Vacuum, Process Cooling Water, Ultra Pure Water, Acid Waste System, & ETC.  Research equipment on UPS or generator power will not be affected. 

Power will be lost to all conference rooms and office areas as well so please plan accordingly to safely power down all office computers and electronic devises in your offices prior to the outage.

All air handling systems, exhaust systems, toxic gas delivery, and monitoring systems will be down beginning at 7 a.m. Monday, October 14 through 4 p.m. Friday, October 18 to complete our preventative maintenance activities.

Please contact Mark Voorhis if you need more detailed information.


MONDAY OCTOBER 14, 2019 BUILDING WIDE ELECTRICAL SHUTDOWN SEQUENCE

  • 8AM – 12PM
    • THE FOLLOWING RESEARCH EQUIPMENT AND AREAS WILL LOSE POWER.
      • ALL OFFICE AND CONFERENCE ROOM AREAS.
      • ALL GENERAL LABORATORIES AND GALLEYS WILL LOSE POWER LISTED BELOW.
        • 1217 1263 2217 2254 1031 1089 1066 2043
        • 1227 1265 2221          1039 1089A 2069 1100A
        • 1233 1267 2233          1043 1069 2031 1153
        • 1235 1269 2239          1045 1092 2077 1157
        • 1237 1273 2261          1077 2087 2081 1154
        • 1239 1261 2277          1081 2087A 2066
        • 1254 1261A 2283        1083 2087B 2037
      • ALL RESEARCH EQUIPMENT IN THE CLEANROOM.
      • ALL RESEARCH SUPPORT EQUIPMENT LOCATED IN THE SUB FAB AREA.
      • THE ULTRAPURE WATER SYSTEM (UPW).
    • ALL EQUIPMENT THAT IS POWERED BY BUILDING WIDE UPS OR GENERATOR POWER WILL NOT LOSE POWER DURING THIS TIME.
  • 11A – 3PM
    • THE FOLLOWING BUILDING WIDE SUB-SYSTEMS WILL LOSE POWER.
      • LOW TEMPERATURE CHILLER SYSTEM
      • COMPRESSED DRY AIR (CDA SYSTEM WILL BE BACKED UP WITH UTILITY NITROGEN)
      • PROCESS VACUUM
      • PROCESS COOLING WATER
      • ACID WASTE NEUTRALIZATION
      • RECLAIM WATER